The first phase of our drainage project will begin on or shortly after December 15, weather dependent. The first phase includes installing new drainage pipes behind homes in Crossvine and Wintercrest East which will drain under the berm and along the drainage ditch at Lassiter Lane. The old drainage pipes will be abandoned. Care will be taken to protect the impacted trees as digging progresses. 

This Phase 1 work will take 5-10 days to complete. Construction debris will be removed. Topsoil and grass seed will be applied on top of the new pipes. 

Phase 2 will begin as budget money is available. Our plan is to work Close by Close addressing issues identified last spring by North Carolina Drainage. Please see the master drainage spreadsheet available on the Countryhouse website for more details on future Close projects. 

The drainage committee appreciates the patience of Countryhouse residents who have been waiting for their drainage issues to be fixed. 

The committee also thanks Michelle and Mill House for their quick turnaround, follow-up and support. Please contact Mill House Properties at hoa@millhouseproperties.com with any questions.

Thank you,
Your Countryhouse Drainage Committee